Project Schedule
To run new H.W.S pipework throughout the school to every outlet, internally and on the roof.
P.I.B lagging to all exterior HTA pipework with trace heating.
Connect to existing plant after converting cylinder to a pressurised system.
Installation of fan convectors and associated builders works.
Installation of duct work and air handling in toilets.
Project Timescale
5 weeks
Project Value
£180K